Airbus must deliver almost 100 aircraft a month to hit 2026 target
4 min read
Airbus will need to deliver almost 100 commercial aircraft every month for the rest of 2026 to meet its full-year target, after August deliveries slipped to 57 aircraft.
The European manufacturer delivered 57 jets to 31 customers during August, taking its year-to-date total to 475 aircraft, according to the latest Airbus orders and deliveries data.
That leaves Airbus with 395 aircraft still to hand over to reach its target of around 870 deliveries this year.
With four months remaining, Airbus needs to average 98.75 aircraft per month from September through December — significantly above the pace achieved so far this year.
However, aircraft deliveries are traditionally heavily weighted towards the final months of the year. Airbus has previously shown it can push large numbers of aircraft across the line in December.
The company delivered 793 commercial aircraft in 2025, meaning its current 870-aircraft target would represent an increase of almost 10%.
August delivery rate falls after stronger summer months
Airbus’ 57 deliveries in August represented a slowdown after a stronger period earlier in the summer.
The manufacturer delivered 89 aircraft in June and 67 in July. Its monthly totals so far in 2026 have been 19 in January, 35 in February, 60 in March, 67 in April, 81 in May, 89 in June, 67 in July and 57 in August.
Despite the latest slowdown, deliveries through August rose 9% to 475, up from 434 in the same period of 2025.

August deliveries comprised:
- 10 A220-300s
- One A319neo
- 16 A320neos
- 26 A321neos
- One A330-900
- Three A350-1000s
The A320neo family remains the backbone of Airbus’ production system, accounting for 43 of the month’s 57 deliveries.
Airbus’ challenge now is to accelerate output significantly during the final four months. An average of almost 99 aircraft per month would be around 73% higher than August’s delivery total.
The required rate is also considerably higher than Airbus’ average of just over 59 aircraft per month during the first eight months of the year.
A330neo deliveries resume after production problem
One positive development in August was the resumption of A330neo deliveries. Airbus delivered a single A330-900 during the month after it halted widebody deliveries in June and July.
The interruption followed the discovery of a tool left inside an aircraft‘s horizontal tailplane during production, prompting Airbus to carry out additional inspections.
Airbus described the issue as isolated, but the inspections disrupted deliveries while affected aircraft moved through the production system.

The manufacturer has delivered only 11 A330s so far this year, 31% fewer than during the equivalent period of 2025. By contrast, A320-family deliveries have increased by 11%.
The production disruption illustrates the difficulty Airbus faces as it attempts to increase overall output. Meeting the 870-aircraft target depends not only on final assembly rates but also on engines, aerostructures, cabin equipment and other components arriving in time for completed aircraft to be handed over to customers.
Airbus nevertheless maintained its 2026 guidance when it published its half-year financial results in July.
At that point, Chief Executive Guillaume Faury said the company was “ramping up across all businesses to meet the growing demand for our civil and military solutions.”
Airbus gains order for 8 A350Fs from undisclosed customer
Airbus’s order book continued to grow in August. The manufacturer recorded 67 gross commercial aircraft orders during August, including a significant deal for eight A350F freighters from an unidentified customer.
The mystery order increases total firm orders for the next-generation freighter from 107 at the end of July to 115.

Eight aircraft constitute a substantial fleet commitment to a programme that has yet to enter commercial service. Cathay Group increased its own A350F commitment to eight aircraft in May when it ordered two additional freighters.
Other August business included:
- 40 A321neos for Shenzhen Airlines
- 15 A350-900s for China Airlines
- Four A220-300s for an undisclosed customer
- One A319neo for an undisclosed customer
During the first eight months of 2026, Airbus received 1,157 gross commercial aircraft orders. Net orders stood at 1,091 aircraft after 66 cancellations.
Airbus faces a demanding final four months
The latest figures leave Airbus in an unusual position: commercial demand remains exceptionally strong, but converting its enormous backlog into deliveries remains the more immediate challenge.
At the end of June, Airbus’ commercial aircraft backlog already stood at 9,222 aircraft. Orders since then have continued to add to that total.
The 870-aircraft delivery target remains achievable, particularly given the manufacturer’s traditional year-end delivery surge. But the arithmetic leaves increasingly little room for further production or supply-chain disruption.
Airbus has completed about 55% of its planned 2026 deliveries with two-thirds of the year gone.
To close the remaining gap, September through December will need to look very different from August. Airbus must deliver roughly 99 aircraft each month, or almost 23 each week, to finish the year at around 870.